NOMARCHIA Station: The works for the installation of metal struts at level -1 were completed, while the excavation of the station’s level -2 is in progress.
NOMARCHIA Crossover: The works for the installation of metal struts at level -1 are in progress.
KALAMARIA Station: Works for traffic arrangements – Phase D – were completed. At the western section, in progress are the works for the construction of the perimeter piles cap beam and for the construction of reinforced concrete struts.
ARETSOU Station: Works for the relocation of EYATH and OTE networks were completed. In progress are the works for the implementation of traffic arrangements – phase A – and for the construction of prestressed anchors for temporary retaining.
NEA KRINI Station: Works for the construction of the slab at level -1 were completed. Works for the construction of walls up to the roof slab, the construction of a fire fighting tank and for the installation of the station’s waterproofing system are in progress.
MIKRA Station: Works for the construction of the piles for the temporary retaining of the staircase were completed.
MIKRA 2nd Crossover: Works for the construction of perimeter piles’ cap beam, as well as preparatory works for the installation of struts at the roof level are in progress.
MIKRA Forestation: Works for the construction of perimeter retaining piles, the configuration of the worksite area, the diversion of PUO networks, as well as preparatory works for traffic arrangement – phase A – are in progress.
Kritis shaft: The construction of the 2nd level metal struts is completed.
The expropriation of areas in ARETSOU, MIKRA (part) Stations and MIKRA Forestation has been completed, while the supplementary expropriation of an area in a small part of MIKRA Station is still pending.