Kritis Shaft: Coloring works and works related to the completion of door installation are in progress.
NOMARCHIA Station: In progress are preliminary reinstatement related works at street level, as well as works for the installation of cabling for the lighting network.
ARETSOU Station: Infrastructure construction works for irrigation and fire-fighting networks have been completed.
Pontou Shaft: Coloring works are in progress.
NEA KRINI Station: Infrastructure construction works for irrigation and fire-fighting networks have been completed.
TRACKWORK: In progress are works for the installation of trunkways – walkways from the area of the Forestation up to NEA KRINI Station.