- NOMARCHIA Station: The works for the construction of retaining piles at the perimeter of the station were completed. The works for the construction of a pile cap beam are in progress;
- KALAMARIA Station: Works for the construction of piles at the western part of the station are in progress;
- NEA KRINI Station: Works for the excavation of the station were completed. The works for waterproofing the station invert are in progress;
- MIKRA Station: The excavation of the 2nd NATM tunnel is completed. The excavation of the 1st NATM tunnel is in progress;
- Preparation and approval of designs is in progress;
- 2nd crossover MIKRA: Investigation trenches and piles’ construction related works are in progress;
- The preparation and approval of designs are in progress;
- The expropriation of areas at ARETSOU Station, at a section of MIKRA Station and at MIKRA Forestation is still pending.