TZAVELA Shaft
The following works have been completed:
- Architectural finishes – Painting works at the staircase (walls, floors).
 - Construction of sound absorbing plaster.
 - Installation of staircase balustrades and balustrades at the street level staircase.
 - Installation of the entrance hatch at street level.
 - Installation of roller shutters.
 - Reinstatement of Tzavela and Lakonias Streets, opening to the
 
The following works are in progress:
- Restoration of minor deficiencies.
 
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street).
 - Installation of glass panels at levels -1, -2.
 - Door painting works.
 - Installation of lifts at street level and at level -2.
 - Installation of lighting poles at the sidewalk of Etolikou Street.
 - Reinstatement of road pavement in Mavromichali Street.
 - Architectural finishes – Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.
 - Installation of steel cladding (panels) on the walls/ceilings and of metal side covers at the station’s escalators.
 - Installation of stainless steel handrails.
 - Installation of the station’s signage.
 - Construction of partition walls at the station’s south expropriation limits (street level)
 - Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street)
 - Slab paving works and installation of paving stones and lighting at street level.
 - Laying of planting soil, planting of trees, bushes and lawn at the station’s flower beds.
 - Connection of the station with EYDAP network.
 - Installation of waste bins, seats (benches), bicycle-motorcycle stands at the square.
 - Removal of worksite fences.
 - Installation of traffic signs and removal of temporary signs that had been installed due to traffic diversions.
 - Opening to the traffic of Etolikou, Koumoundourou, Dimitrakopoulou, Gythiou and Mavromichali Streets.
 
The following works are in progress:
- Restoration of minor deficiencies.
 
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Steel cladding on the roof and side covers.
 - Installation of information boards and signage at the platforms.
 - Installation of seats at the platforms.
 - Installation of radio communication (TETRA) cable.
 
The following works are in progress:
- Restoration of minor deficiencies.
 
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Installation of granites and stainless ducts (gutters).
 - Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
 - Installation of lifts glass panes.
 - Installation of metal side covers and handrails at the station’s escalators.
 
The following works are in progress:
- Restoration of minor deficiencies.
 
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Construction of perimeter wall at the boundaries of the expropriation.
 - Construction of metal structures at K.P. +8.36 and +21.00.
 - Construction of sound absorbing plaster.
 - Installation of staircase balustrades – handrails.
 - Architectural finishes (re-painting works).
 - Door painting works.
 - Installation of access hatch at the street level.
 - Road surface reinstatement, opening to traffic of Koumoundourou Street, installation of lighting bollards, waste bins and seats.
 
The following works are in progress:
- Restoration of minor deficiencies.
 
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Installation of metal structures at K.P. +8.08 and +24.98.
 - Construction of sound absorbing plaster.
 - Architectural finishes (re-painting works).
 - Door painting works.
 - Installation of staircase balustrades – handrails.
 - Installation of the entrance hatch at street level.
 - Construction of perimeter parapet walls at the boundary of the expropriation.
 - Road surface reinstatement, opening to traffic of Dimitrakopoulou Street, installation of lighting bollards, waste bins, and seats and planting of trees.
 
The following works are in progress:
- Restoration of minor deficiencies.
 
MELA SHAFT
The following works have been completed:
- Painting works at the staircase and the remaining areas.
 
The following works are in progress:
- Still pending is the reinstatement of the square’s area that had been occupied.
 
PIRAEUS STATION
The following works have been completed:
- Painting works at the station.
 - Construction of fillings and industrial floors.
 - Installation of metal doors.
 - Installation of granites.
 - Walls and columns lining.
 - Installation of false ceilings.
 - Installation of galvanized metal panels.
 - Backfilling of entrances.
 - Installation of lifts.
 - Construction of sidewalks and installation of granites and marbles at street level.
 - Construction of sub-base and asphalt laying works.
 - Planting works and installation of irrigation system.
 - Installation of trays at street level.
 
The following works are in progress:
- Reinstatement of ISAP area.
 - Reinstatement of OLP area.
 
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Sealing of the temporary pumping station.
 - Installation of emergency exit hatch at street level.
 
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Opening of V. Georgiou and Karaiskou Streets to the traffic.
 - Installation of false ceiling at the ticketing level and at the platform level.
 - Installation of floor granites at the ticketing level.
 - Construction of stainless cladding, stanchion and balustrades at the ticketing level, at the platform level and the staircases.
 - Installation of ironmongery on the doors.
 - Conservation of the Project’s archaeological finds.
 
The following works are in progress:
- Reinstatement at street level (slab paving works, planting works, irrigation network for planting areas etc.).
 - Painting of the floor of the mechanical level and re-painting works of the walls of the technical rooms
 
STAIRCASE GALLERIES
The following works are in progress:
- Installation of supports and wall and ceiling panels.
 - Installation of handrails at the staircases.
 - Installation of floor granites.
 
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Construction of lift housing structure at street level.
 - Removal of worksite offices from the surface level.
 - Installation of wall and ceiling panels.
 - Implementation of the design for the display of the archaeological finds in the recess.
 
The following works are in progress:
- Reinstatement at street level.
 
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works are in progress:
- Installation of wall and ceiling panels.
 - Implementation of the design for the display of the archaeological finds in the recess.
 
DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY
The following works have been completed:
- Sealing of the temporary pumping station.
 - Sidewalk traffic reinstatement on V. Georgiou Street.
 - Removal of sidewalk in the framework of the implementation of the permanent traffic study.
 - Painting of the floor of the connecting tunnel.
 
TRIPLE TRACK NATM TUNNEL
Works have been completed.
DELIGIANNI SHAFT
The following works have been completed:
- Disassembly of building crane.
 
The following works are in progress:
- Reinstatement at street level.
 
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works are in progress:
- Reinstatement at street level.
 
