Thessaloniki Base Project progress

March 2016

Dimokratias Crossover: The works for the excavation of the final level -3 are in progress. DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress. AGHIA SOFIA Station: The works for the construction of anchors for the temporary retaining of the southern access and the general excavation…
Μάθε Περισσότερα

February 2016

Dimokratias Crossover: The works for the construction of level -2 were completed, while the preparation for the excavation of level -3 is in progress. DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress. SINTRIVANI Station: Preparatory works for the excavation of level -4 are in progress.…
Μάθε Περισσότερα

January 2016

PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls are in progress. VOULGARI Station: The works for the POY network diversions, traffic arrangements and worksite installations are in progress. NEA ELVETIA Station & Crossover: At the crossover, the construction of the foundation slab is completed, while the…