Thessaloniki Base Project progress

January 2018

NEW RAILWAY Station: The installation of escalators at the accesses has been completed. In progress are works for the implementation of traffic phase E’, as well as the works for the installation of doors and E/M installations (sewage network). • DIMOKRATIAS Station: The construction of the north access and the…
Μάθε Περισσότερα

April 2017

• NEW RAILWAY Station: The archaeological excavation at the south shafts is complete. The excavation and the temporary retaining of the southern shaft are in progress. • DIMOKRATIAS Station: The construction of the temporary retaining at the southern access is in progress. • SINTRIVANI Station – EXPO: The construction of…
Μάθε Περισσότερα

December 2016

• Dimokratias Crossover: Works for the construction of the foundation slab at the northern part have been completed. • SINTRIVANI Crossover: Works for the concreting of provisional openings are in progress. • PANEPISTIMIO Station: Works for the construction of masonry walls at level -1 have commenced. • PAPAFI Station: Works…
Μάθε Περισσότερα

November 2016

NEOS SIDIRODROMIKOS STATHMOS Station: In progress are masonry works at level -1. Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while works for the construction of the foundation slab are in progress at the northern part. DIMOKRATIAS Station: In progress is the archaeological…
Μάθε Περισσότερα

October 2016

NEOS SIDIRODROMIKOS STATHMOS Station: In progress is the archaeological excavation at the southeast and southern shaft, as well as the installation of escalators. Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while there are still in progress at the southern part. DIMOKRATIAS Station:…
Μάθε Περισσότερα

September 2016

NEW RAILWAY Station: Excavation works at the southern access are in progress. DIMOKRATIAS Crossover: The works for the construction of the foundation micro-piles are in progress. DIMOKRATIAS Station: Traffic arrangements at Monastiriou Street have been completed. The works for the construction of the raft are in progress while archaeological excavations…
Μάθε Περισσότερα

August 2016

NEW RAILWAY Station: The works for the construction of retaining piles in the shafts and the diversion of the combined-flow network are in progress. DIMOKRATIAS Station: the excavation works are completed, while in progress are the preparatory works for the subsequent traffic phase. AGHIA SOFIA Station: The works for the…
Μάθε Περισσότερα

June 2016

Dimokratias Crossover: Works for the excavation of the final level are in progress. DIMOKRATIAS Station: Completion of the construction of slab -2. Moreover, in progress is the archaeological excavation of the final level. SINTRIVANI Station – REPORT: In progress is the temporary retaining of the northern access. PAPAFI Station: In…
Μάθε Περισσότερα

May 2016

Dimokratias Crossover: The works for the installation of struts at the final level are in progress. DIMOKRATIAS Station: Completion of excavation works at level -2 of the station. In progress is the construction of slab -2. Moreover, in progress is the archaeological excavation of the northern access, the northern ventilation…
Μάθε Περισσότερα