Thessaloniki Base Project progress

December 2012

Both TBMs have completed the construction of the twin tunnel of an overall length of 11,300m (single track) from NEW RAILWAY STATION up to ANALIPSI Station; Archaeological excavations at VENIZELOU and DIMOKRATIAS Stations are at a completion stage; Civil Works have been completed at the forestation of the NEW RAILWAY…
Μάθε Περισσότερα

July 2012

The construction of inner parapet walls at EFKLIDIS Station is in progress. The excavation works at FLEMING Station are in progress. The construction of diaphragm walls at ANALIPSI Station is in progress. The ground slab at the 2nd basement of PANEPISTIMIO Station has been completed. The construction of the roof…
Μάθε Περισσότερα

June 2012

Until the present day, seventy-four per cent (74%) of the archaeological excavations has been carried out and by the end of 2012 all excavation works are expected to be completed. During the archaeological survey, more than 10,000 finds have been revealed, especially along Egnatia Odos. At the current phase, archaeological…
Μάθε Περισσότερα

April 2012

The completion percentage of the Civil Works for THESSALONIKI METRO Project reaches 42%, while the tunneling completion percentage is over 72%. The architectural finishes works, as well as the works for the installation of the electromechanical equipment of the Project have recently commenced. The archaeological excavations at four (4) locations…
Μάθε Περισσότερα