NOMARCHIA Station: The construction of the permanent lining from the foundation slab up to level -2 is in progress.
NOMARCHIA Crossover: The construction of the permanent lining from the foundation slab up to level -1 was completed. In progress is the construction of the slab of level -1 and the removal of struts of the second level
ARETSOU Station: The excavation and temporary retaining of the station has been completed. In progress is the construction of the foundation slab.
Pontou shaft: The excavation and the temporary retaining up to level -2 are in progress.
NEA KRINI Station: In progress is the construction of the masonry walls at level -1.
1st Crossover and Section of MIKRA Station: The excavation and temporary retaining have been completed. The waterproofing of the perimeter walls and the construction of the foundation slab is in progress.
2nd Crossover and Section of MIKRA Station: The construction of the final level of anchors is in progress.
MIKRA Forestation – Section 01: The installation of the 2nd level struts has been completed. Section 03 – 05: The construction of the 3rd row of anchors has been completed. Excavation up to the 4th row is in progress. Section 08-09: The excavation up to the 2nd level is in progress.
Terminal shaft: The installation of the steel struts of the 2nd level is in progress.
The preparation and approval of designs are in progress.