- NEW RAILWAY Station: Excavation works at the southern access are in progress.
- DIMOKRATIAS Crossover: The works for the construction of the foundation micro-piles are in progress.
- DIMOKRATIAS Station: Traffic arrangements at Monastiriou Street have been completed. The works for the construction of the raft are in progress while archaeological excavations have commenced at the southern access.
- SINTRIVANI Station – THESSALONIKI EXPO: The works for the construction of the raft are in progress.
- EFKLEIDIS Station: Masonry works are in progress.
- FLEMING Station: In progress is the construction of the raft.
- ANALIPSI Station and Crossover: In progress are works for the construction of the roof slab at the northern shaft, as well as preparatory works for the subsequent traffic phase.
- VOULGARI Station: Preparatory works for the subsequent traffic phase are in progress.
- PATRIKIOU Station and Crossover: Traffic has been reinstated at 25 Martiou Street while in progress are works for the construction of the roof slab at the northern shaft.
- VOULGARI Station: Preparatory works for the construction of the roof slab are in progress.
- DEPOT
Building Complex I: Masonry works at level 0 and plastering works at levels -1 and -2.
Building Complex II: Archaeological works in the area of the entrance to the Depot are in progress. - C/C Tunnel: Section II: Pile cap beam installation works are in progress. Section III: Investigation works at the periphery trench are completed.