- The organization of individual worksites at several locations along the Tramway Extension to Piraeus (Lambraki Avenue U-turn, Karaiskaki Bridge) has commenced;
- Works for replacing the canopy of the workshop at Building No. 1 have been completed; architectural finishes and electromechanical works at Building No. 2 are at an advanced stage; dismantling works in areas of Building No. 1, in the Tramway Depot Building facilities in Elliniko, are in progress;
- The works for the completion of the bearing structure of the W.C. building complex in the land plot of the playground in the area of Rizareios – P. Faliro are at an advanced stage.