- NOMARHIA Station & Crossover: The works for the construction of pits for the diversion of the central sewage pipe, the works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp, as well as the works for the diversion of PUO networks are at an advanced stage;
- KALAMARIA Station: The works for the diversion of PUO networks, as well as the works concerning traffic arrangements are in progress;
- NEA KRINI Station: The construction of the Station’s retaining works, as well as the excavation of the Station at a depth of approximately 9m are in progress;
- MIKRA Station: The works for the diversion of PUO networks have commenced, while the construction of temporary retaining works (prestressed anchors, shotcrete), as well as the worksite installations are in progress;
- Kritis Shaft: The works for the implementation of traffic arrangements have commenced;
- The preparation of designs is in progress;
- The expropriation of an area at ARETSOU, NEA KRINI Stations and at MIKRA Forestation, is still pending.