The works for the diversion of EYATH and Lighting networks in the area of NEOS SIDIRODROMIKOS STATHMOS were completed.
The works for the construction of the guides of the diaphragm walls were completed at the TBM Start-up Shaft in the area of NEOS SIDIRODROMIKOS STATHMOS.