Thessaloniki Base Project progress

Οctober 2009

  • The first TBM (TBM1) has constructed 2600m of tunnel and approaches SINTRIVANI Station, while the second (TBM2) has constructed 1700m. of parallel tunnel and moves towards AGHIA SOFIA Station.
  • Works related to the construction of the roof slab at PANEPISTIMIO Station as well as at the forestation of NEOS SIDIRODROMIKOS STATHMOS commenced.
  • Works related to the construction of the metal bridge at VENIZELOU and AGHIA SOFIA Stations are in progress.