- Until the end of February 2011 both TBMs have constructed in total 8,450 meters of a completed (single-track) tunnel.
- The works for the construction of a temporary metal bridge at the northern section of “Dimocratias” Station are in progress.
- The works for the construction of micro-piles at the foundation slab level in “Efklidis” Station are in progress.