AGHIA SOFIA Station: The archaeological excavation at the southern part of the station is in progress.
SINTRIVANI Station: Excavation works at level 3, as well as the works for the construction of a NATM ventilation tunnel, are in progress.
PAPAFI Station: Excavation works at level 3, as well as the works for the installation of the 3rd row of struts, are in progress.
FLEMING Station: The works for the installation of the last row of struts are in progress.
Depot: The works for the construction of bored piles, as well as for the installation of steel reinforcement at the remaining part of building I, were completed.