Dimokratias Crossover: Works for the excavation of the final level are in progress.
DIMOKRATIAS Station: Completion of the construction of slab -2. Moreover, in progress is the archaeological excavation of the final level.
SINTRIVANI Station – REPORT: In progress is the temporary retaining of the northern access.
PAPAFI Station: In progress are the works for the construction of the invert slab and the waterproofing of the walls above the invert slab.
FLEMING Station: In progress is the construction of foundation micropiles.
ANALIPSI Station and Crossover: In progress are preparation works for the arrival of the two TBMs at the crossover.
DEPOT: At building complex I, in progress is the construction of the bearing structure and the masonry walls at level -2. At building complex II, in progress is the construction of the bearing structure of building 6.
Cut and Cover Tunnel: Excavation works and temporary retaining works are in progress.