ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. – ELLINIKO METRO S.A.

Καλαμαριά Απρίλιος 2026
Kalamaria Project progress

April 2026

Kritis Shaft: Works related to infrastructure (transfers, trays) and distribution (switchboard connections) have been completed.

NOMARHIA Station (Station & Crossover): In progress are electromechanical works related to infrastructure (trays), earthing (ducts), distribution (connections of equipment – switchboards), lighting (cables, lighting fixtures), hydraulic (pumping station), lifts (certification, construction), radio communications (antennas, tests), surveillance systems (tests), low voltage (field equipment, cables, connections) and fare related works (fibers). In the Crossover area, works related to infrastructures and the largest part of the electromechanical related works have been completed. Moreover, works related to distribution (switchboard connections), lighting (cables, lighting fixtures, electrical material), ventilation (air ducts) and low voltage (field equipment, cables, connections) have been executed.

KALAMARIA Station: In progress are electromechanical works related to infrastructure (trays), earthing (ducts), distribution (connections of equipment – switchboards), lighting (cables, lighting fixtures), hydraulics (pumping station), escalators (connections), radio communications (antennas, tests), surveillance systems (tests), low voltage (field equipment, cables, connections) and fare related works (fibers).

ARETSOU Station: In progress are electromechanical works related to earthing (ducts), lighting (cables, lighting fixtures), firefighting (tests), lifts (certification, construction), radio communications (antennas, tests), surveillance systems (tests, connections), low voltage (field equipment, cables, connections), as well as fare related works (fibers).

NEA KRINI Station: In progress are electromechanical works related to earthing (ducts), lighting (cables, lighting fixtures), firefighting (tests), lifts (metal frames), radio communications (antennas, tests), surveillance systems (tests, connections), low voltage (infrastructures, cables, connections), as well as fare related works (fibers).

MIKRA Station: In progress are electromechanical works related to the infrastructure (trays), works related to earthing (ducts), distribution (connections of equipment – switchboards, controls – settings of switchboards), lighting (cubicles, cables, lighting fixtures), smoke exhaust (setting into operation, controls), air conditioning (piping), water supply (piping), fire detection (cables), surveillance systems (fiber optics) and low voltage (infrastructures, cables, connections).

Forestation – Terminal Shaft: At the completion stage are the electromechanical distribution works, the hydraulic works, as well as the works for interconnection with the central surveillance systems.

Tunnels: Completed are all infrastructure and trackwork related activities, as well as the electromechanical works pertaining to medium voltage distribution, earthing, traction, lighting and firefighting systems.