Καλαμαριά Ιανουάριος 2026
Kalamaria Project progress

January 2026

Kritis Shaft: Infrastructure (grids, earthing), lighting (cubicles, cables, lighting fixtures) and distribution works have been executed, while a section of the ventilation panels was also installed.

NOMARHIA Station (Station & Crossover): In progress are the electromechanical works related to infrastructure (grids), distribution (installation – measurements – connection of supply cables, installation of ventilation panel, inspection of general LV and MV switchboards in LAS Substation), lighting (cubicles, cables, lighting fixtures), ventilation (air ducts, dampers, fans, supports), air conditioning (fixing of split-type units), lifts (electrical works, lift house), surveillance systems (signals cables), and low voltage (trays, cables, connections, cubicles). In the Crossover area, infrastructure works (grids, earthing), lighting (cubicles, cables, lighting fixtures) have been executed.

KALAMARIA Station: In progress are electromechanical works related to infrastructure (grids), distribution (installation – measurements – connection of supply cables, installation of ventilation panel, inspection of general LV and MV switchboards in LAS Substation), lighting (cubicles, cables, lighting fixtures), ventilation (air ducts, dampers, fans, supports), air conditioning (fixing of split-type units), radio communication (controls, measurements), surveillance systems (signals cables), low voltage (trays, cables, connections, cubicles).

ARETSOU Station: In progress are works for the completion of architectural finishes and reinstatement works at street level. Moreover, continued are electromechanical works related to infrastructure (grids, earthing), distribution (connection of supply cables, installation of ventilation panel, inspection of general LV and MV switchboards in LAS Substation), lighting (cubicles, cables, lighting fixtures), ventilation (air ducts, supports), air conditioning (fixing of split-type units), automatic fire extinguishing (inspections), fire detection (field equipment, connections), surveillance systems (signals cables) and low voltage (trays, cables, connections, cubicles).

NEA KRINI Station: In progress are electromechanical works related to infrastructure (grids, earthing), distribution (connection of supply cables, installation of ventilation panel, inspection of general LV and MV switchboards in LAS Substation), lighting (cubicles, cables, lighting fixtures), ventilation (dampers, air ducts, supports), air conditioning (fixing of split-type units), firefighting (tests), radio communication (controls, measurements), surveillance systems (signals cables)

MIKRA Station: In progress are electromechanical works related to distribution (installation of ventilation panels, inspection of general LV and MV switchboards in LAS substation), lighting (cables), ventilation (air-ducts, dampers, fans, supports), air conditioning (fixing of split-type units), escalators (controls, maintenance), surveillance systems (signals cables), low voltage (trays, cables, connections, racks).

Tunnels: All infrastructure and trackwork related activities have been completed, as well as the electromechanical works pertaining to medium voltage distribution, earthing, traction and firefighting systems.