Καλαμαριά Αύγουστος 2025
Kalamaria Project progress

August 2025

  • Kritis Shaft: All infrastructure related activities of this section have been completed. In progress are the works pertaining to the completion of lighting, fire detection, communication systems, ventilation, air-conditioning, hydraulic and low voltage distribution systems.
  • NOMARHIA Station: All infrastructure related activities of this Station have been completed. In progress are the works pertaining to the completion of architectural finishes, hydraulics and reinstatement at street level. The medium voltage electrotechnical works at the Station are at the completion stage along with firefighting, automatic fire extinguishing, escalators and PSD systems. In progress are the works pertaining to the completion of low voltage distribution & earthing systems, sewage-pumping stations, fire detection, lighting, air-conditioning–ventilation systems, lifts and communication systems.
  • KALAMARIA Station: All infrastructure related activities of this Station have been completed. In progress are the works pertaining to the completion of architectural finishes, hydraulics and reinstatement at street level. At their completion stage are the electromechanical works pertaining to medium voltage, earthing system, water supply-sewage-pumping stations, firefighting, automatic fire extinguishing, escalators and PSD systems. In progress are the works pertaining to the completion of low voltage distribution and LAS equipment, fire detection, lighting, air-conditioning–ventilation systems, lifts and communication systems.
  • ARETSOU Station: All infrastructure related activities of this Station have been completed. In progress are the works pertaining to the completion of architectural finishes and reinstatement at street level.  At their completion stage are the electromechanical works pertaining to medium voltage, earthing system, water supply-sewage-pumping stations, firefighting, automatic fire extinguishing, ventilation and air-conditioning systems, escalators and PSD systems. In progress are the works pertaining to the completion of traction power, low voltage distribution and LAS equipment, fire detection and lighting, lifts and communication systems.
  • Pontou Shaft: All infrastructure related activities of this section have been completed, while in progress are the works pertaining to the completion of lighting, earthing systems and roller shutters.
  • NEA KRINI Station: All infrastructure related activities of this Station have been completed. In progress are the works pertaining to the completion of architectural finishes and reinstatement at street level. At their completion stage are the electromechanical works pertaining to medium voltage, water supply-sewage-pumping stations, firefighting, automatic fire extinguishing, escalators and PSD systems. In progress are the works pertaining to the completion of low voltage distribution and LAS equipment, earthing systems, fire detection, lighting, air-conditioning–ventilation systems, lifts, communication and Taction Current Removal (TCR) systems.
  • MIKRA Station: All infrastructure related activities of this Station and both Crossovers have been completed. In progress are the works pertaining to the completion of architectural finishes and reinstatement at street level. At their completion stage are the electromechanical works pertaining to medium voltage, traction power, water supply-sewage-pumping stations, firefighting, automatic fire extinguishing, escalators and PSD systems. In progress are the works pertaining to the completion of low voltage distribution and LAS equipment, earthing system, fire detection, lighting, air-conditioning–ventilation systems, lifts, communication and Taction Current Removal (TCR) systems.
  • MIKRA Forestation – Terminal Shaft: All infrastructure related activities of this section have been completed, while in progress are the works pertaining to the completion of lighting, earthing systems, hydraulics ventilation and communication systems.
  • Tunnels: All infrastructure and trackwork related activities of this section have been completed. At their completion stage are the works pertaining to lighting, firefighting and communication systems. In addition, at their completion stage are the electromechanical works pertaining to medium voltage cabling, earthing systems, tunnel traction power system, firefighting and central cabling.