Kalamaria Project progress

May 2025

NOMARCHIA Station: In progress are works related to the ventilation network (air ducts, fans, sound attenuators, dampers). In the area of Nomarchia crossover, in progress are spatial arrangement works for the installation of the switchboard at the traction power distribution network.
KALAMARIA STATION: In progress are works related to the ventilation network (air ducts, fans, sound attenuators, dampers) as well as works for the addition of louvers in the air exhaust fans at the platform area.
ARETSOU STATION: Works for the installation of trays inside the ventilation room as well as earthing, lighting and traction power distribution works are being continued. Moreover, in progress are granite finishes works in all station levels.
NEA KRINI STATION: In progress are earthing works at the fire-detection system, lighting works, as well as ventilation and signaling works. In progress are granite finishes works in all station levels.
Tunnels: Measurements of the continuation of the 3rd rail in all tunnel subsections are being continued.