ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. – ELLINIKO METRO S.A.

KALAMARIA_03_2025
Kalamaria Project progress

March 2025

NOMARCHIA Station (Station and Crossover): In progress are works for the installation of electric motors at the fire resistant motorized dampers, at the ventilation shafts as well as power supply and fire detection cabling works. Moreover, in progress are works for the installation for power supply cables from the station to the switchboards of the crossover. At the crossover, in progress are works for the connection of low voltage cables at the Rectifier Substation (RS), as well as earthing works in the substation.
KALAMARIA Station: In progress are works for the installation of water heaters and of a Fan Coil Unit (FCU), as well as works for the trial chlorination of the water network up to EYATH manhole.
ARETSOU Station: Completed are works for the installation of DC cables in the Rectifier Substation. In progress are works for the installation of electric motors of the fire resistant motorized dampers at the ventilation shafts, as well as earthing and equipment bases works in the Rectifier and LAS Substations.
NEA KRINI Station: In progress are granite finishes works in all station levels, as well as the trial chlorination of the water supply network up to EYATH manhole.
MIKRA Station: In progress are road surface reinstatement works in the station area (of sidewalk and the central traffic island finishings), as well as granite finishes works in all station levels. Moreover, in progress are works at trays and low voltage cables at the Rectifier Substation.
TRACKWORK – TUNNELS: At ARETSOU – NEA KRINI interstation, in progress are lighting cabling system works.