NOMARCHIA Station (Station and Crossover): In progress are works for the implementation of the final traffic reinstatement (configuration of traffic islands and sidewalks) as well as painting works at street level.
ARETSOU Station: Completed are works for the installation of glass panes, as well as the installation of doors at platform level, while in progress are slab paving works at street level.
NEA KRINI Station: Completed are works for the installation of glass panes, as well as works for the installation of doors at the platform level.
MIKRA Station (Station and Crossovers): In progress are road paving and slab paving works at street level, as well as works for the installation of glass panes at the concourse level.