Καλαμαριά Ιούνιος 2023
  • NOMARCHIA Station (Station & Crossover): In progress are works for the installation of sound insulation made of mineral wool in the tunnel ventilation equipment rooms of the, as well as works for the installation of rails intended for the suspension of equipment of the tunnel ventilation system. In the area of the Crossover, in progress are works for the installation of trays and earthing activities.
  • KALAMARIA Station: In progress are works for the installation of glass panes on the stainless steel balustrades and works for the installation of sound insulation made of mineral wool at the tunnel ventilation equipment areas. Moreover, in progress are works for the installation of the automatic platform screen doors and works for the installation of rails intended for the suspension of equipment of the tunnel ventilation system,
  • ARETSOU Station: In progress are works for the installation of glass panes at levels -1 and -3, slab-paving works and works for the construction of the infrastructure of the lighting and irrigation networks at street-level, as well as works for the installation of rails for the suspension of equipment of the tunnel ventilation system Moreover, completed are cabling works at the PSD system and works for the installation of trays, earthing of trays and cabling of the lighting network at platform level.
  • NEA KRINI Station: Completed are works for the installation of granite floor at platform level, works for the installation of raised floor in the UPS equipment and in the signaling equipment rooms. Moreover, completed are cabling works and stand-alone tests at the PSD system.
  • MIKRA Station: Completed are cabling works and stand-alone tests at the PSD system, as well as works for the installation of trays, earthing of trays and cabling of the lighting network at platform level. In progress are works for the installation of glass panes at level -1, and slab-paving works, as well as works for the construction of the infrastructure of the lighting and irrigation networks at street-level.