Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Καλαμαριά Μάρτιος 2023
  • NOMARCHIA Station: In progress are works for the installation of granites at platform level, works for the construction of the sewage system and the installation of the automatic fire fighting network, as well as works for the installation of rails for the suspension of equipment of the tunnel ventilation system.
  • KALAMARIA Station: In progress are works for the completion of the installation of escalators 3a, 3b & 4a, 4b, works for the installation of rails for the suspension of equipment of the tunnel ventilation system, as well as preparatory works for the installation of columns of the automatic PSN door system.
  • ARETSOU Station: In progress are works for the installation of PSDs, as well as works for the installation of rails for the suspension of equipment of the tunnel ventilation system.
  • NEA KRINI Station: Completed are works for the installation of trays, earthing of trays and cabling of the lighting network at platform level.
  • MIKRA Station: In progress are works for the completion of the installation of outdoor escalators, cabling works of the PSD system, as well as works for the installation of the fire detection system.
Print Friendly, PDF & Email
WCAG