March 2023

Καλαμαριά Μάρτιος 2023
  • Kritis Shaft: In progress are street level reinstatement works and works for the installation of skirting and steel balustrades.
  • NOMARCHIA Station: In progress are painting works of terminations at street-level and works for the installation of the sewage system, while works for the installation of Platform Screen Doors (PSDs) have been completed.
  • ARETSOU Station: In progress are works for the installation of PSDs and waterproofing works.
  • NEA KRINI Station: In progress are works for the installation of stainless steel balustrades, the installation of the fire-detection system, the installation of fire-rated air ducts above the PSDs, and works for the installation of air ducts and the equipment of the ventilation/ air-conditioning system.
  • MIKRA Station (Station and Crossovers): In progress are works for the construction of gypsum board lining above the PSDs. Moreover, in progress are works for the construction of fire-rated air ducts above the PSDs, works for controlling the installation of PSDs and works for the installation of equipment and air ducts for the ventilation/ air-conditioning system. In the area of the 2nd Crossover, in progress are works for the installation of sound proof lining and works for the construction of infrastructures for the lighting and irrigation networks at street level.
  • TRACKWORK: In progress are works for the installation of electrical trays at interstations 4 and 6 and in the area of the pumping stations.