Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

December 2022

Θεσσαλονίκη Δεκέμβριος 2022
  • New Railway Station: Completed are works for the installation of the raised floor and the equipment in the Station Master Room (SMR), as well as works for the invert concrete laying at the platform. In progress are works for the installation of the false ceiling suspension system in public areas (concourse level), marble cladding construction works in public areas, as well as works for the reinstatement of the surrounding area in the north access area.
  • DIMOKRATIAS Station: Completed is the installation of the raised floor and the equipment in the SMR, as well as the works for the invert concrete laying at the platform. In progress are works for the construction of marble cladding at the eastern staircase, painting works, works for the installation of electric ducts, as well as works for the installation of traction power and lighting cables.
  • VENIZELOU Station: Completed are works for the construction of the invert slab and the construction of inner parapet walls made of reinforced concrete down to level -3 slab. In progress are works for the construction of parapet walls and of the platform slab, the inner walls between levels -3 and -2, as well as works for the construction of trumpets of the station with the tunnels. In progress is the archaeological survey at the two accesses (north and south) of the station.
  • AGHIA SOPHIA Station: Completed are the works for the re-installation of the Krineon-Nymphaeum building in the station’s northern access area, the works for the installation of the Platform Screen Doors (PSD) at track 2, the installation of the elevated floor in the Station Master Room (SMR), as well as the installation of the station’s traction power supply equipment. In progress are works for the completion of the 1st stage of painting works, the installation of PSDs at track 1, as well as works for the installation of trays and cables at all station levels.
  • SINTRIVANI Station: Completed are the final reinstatement works at street level, the installation of systems related to fire detection and telecommunications equipment in public areas (cameras, loudspeakers, Passenger Information System (PIS) etc.), as well as the installation of the elevated floor in the Lighting and Auxiliary Equipment Substation (LAS) area. In progress are final painting works, works for the completion of the installation of false ceilings using perforated panels, works for the installation of side-lining of escalators at the platform, as well as works for the installation of the mimic panels of the tunnel ventilation system and the stations ventilation/air conditioning system.
  • PANEPISTIMIO Station: Completed are works for the construction of the false ceiling at the central staircase, while in progress are works related to the final painting and the construction of false ceilings at levels -1, -2 and -3.
  • PAPAFI Station: Completed are the works for the installation of the architectural lining above the PSDs, the final painting works, as well as the works for the connection of the mimic panel of the ventilation/air conditioning system. In progress are the works for the construction of sheds at street level, works for the installation of equipment in the personnel’s rest room, works for the installation of ironmongery, as well as works for the construction of routings for Persons with Special Needs (PSN) in the public areas.
  • EFKLIDIS Station: Completed are works for the installation of the architectural lining above the PSDs, the installation of the ventilation/air conditioning system mimic panel, as well as the installation of the Uninterrupted Power Supply (UPS) equipment and batteries for the lighting system. In progress are the final painting works, the works for the construction of false ceilings and the installation of non-perforated steel lining sheets, the works for the installation of equipment in the personnel’s rest room, works for the installation of ironmongery, works for the construction of routings for PSNs in the public areas, as well as works for the construction of sheds at the surface.
  • FLEMING Station: Completed are works for the installation and connections of the lighting switchboards in the area of the Lighting and Auxiliary Substation (LAS), as well as works for the installation of the equipment of the uninterrupted power supply and batteries for the lighting system. In progress are final painting works, works for the construction of false-ceiling, of the installation of vertical lining using aluminum panels and works for the completion of the installation of the fire-detection and of the access control / intrusion detection systems.
  • ANALIPSI Station: Completed are works for the installation of removable balustrades and works for the installation and connections of the general low voltage switchboard. In progress are final painting works, works for the construction of fire dampers, works for the installation of raised floors and metal floors in the ventilation shafts, works for the installation of air ducts and of the equipment of the ventilation/ air conditioning and tunnel ventilation systems, works for the installation of lighting cables and equipment installation works in the Station Master Room.
  • 25 MARTIOU STATION: Completed are vertical marble cladding works, works for the installation of removable balustrades, construction works of the passages for PSNs in public areas, equipment installation works in the Station Master Room and works for the construction of the gypsum fiber false ceiling at the accesses. In progress are surface reinstatement works in the branching area, works for the construction of fire-dampers in the station, final painting works, and works for the completion of the installation of the air ducts, the ventilation/air-conditioning system and the tunnel ventilation equipment, works for the installation of the mimic panels of the tunnel ventilation system and the MLU lighting switchboard.
  • VOULGARI Station: Completed is the construction of the passages for PSNs in public areas and works for the installation of furniture in the Station Master Room. In progress are works for the installation of the vertical aluminum lining panels in public areas, works for the construction of fire dampers, final painting works and works for the installation of the automatic fire extinguishing system/gas and for the installation of cables.
  • NEA ELVETIA Station: Completed are works for the installation of the equipment in the Station Master Room, while in progress are works for the construction of fire dampers and works for the installation of suspension tracks for the pumping station equipment.

DEPOT

Building Complex Ι: Completed are works for the installation of the interior lining panels. In progress are works for the installation of exterior aluminum louvers and works for the installation of covers for seismic joints. With regard to electromechanical installations, in progress are works for the installation of lifts and works for the installation of cables of the CCVT and BACS systems.

Building Complex ΙΙ: With regard to the Administration Building and the Control Centre, completed are works for the installation of stainless steel food benches in all the food and beverage rooms at all levels. In progress are painting works, lining works using ceramic tiles, works for the installation of steel stripe false ceilings in the sanitary rooms and in the food and beverage room, works for the installation of mineral fiber false ceiling in the office rooms, works for the installation of the remaining exterior frames and the interior aluminum glass panels, as well as works for the installation of stainless steel lining on the walls of the lifts at all levels. In Building 2, in progress are painting works, works for the installation of glass panels and the interior aluminum glass panels, works for the installation of exterior aluminum louvers and works for the installation of exterior lining using aluminum panels. With regard to the electromechanical works, in progress are the works for the installation of air ducts, works for the insulation of the air conditioning pipes, works for the installation of lifts and works for the installation of air conditioning pipes. In the surrounding area, in progress are works for the arrangement of the Public Utility Organizations networks, works for the construction of curbs, sidewalks and gutters in the framework of the reinstatement of Possidonos Street.

TRACKWORK:

In progress are works for the connection of the track-side signaling equipment from the NEW RAILWAY Station up to DIMOKRATIAS Station.

In progress are testing and commissioning works.

Print Friendly, PDF & Email
WCAG