- KALAMARIA Station: In progress are works for the installation of stainless steel balustrades.
- ARETSOU Station: In progress are works for the installation of the Platform Screen Door (PSD) system.
- NEA KRINI Station: In progress are works for the installation of storm and waste water pumps, collectors and discharge networks.
- MIKRA Station: In progress are works for the installation of networks and equipment for the ventilation / air conditioning system.
TRACKWORK:
In progress are works for the installation of the fire fighting network at interstation 1 / track 2, as well as works for the installation of electrical trays at interstations 3 and 4 / track 2.