ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. – ELLINIKO METRO S.A.

JANUARY 2021
Piraeus Project progress

JANUARY 2021

 

MANIATIKA STATION

STATION’s OPEN CUT

The following works have been completed:

  • Completion of the permanent lining of the shaft

The following works are in progress:

  • Waterproofing of the roof slab
  • Masonry walls – plastering works at levels -4, -3, -2 and -1
  • Architectural finishes – Painting works at level -4
  • Industrial flooring at levels -4, -3 and -2

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Permanent lining of the station’s main tunnel
  • Permanent lining of the deepening area
  • Permanent lining of the northern and southern headwall
  • Construction of parapet walls and platform slabs
  • Secondary grouting of the vault of the main station tunnel
  • Filling of platform ducts with non-reinforced concrete.

The following works are in progress:

  • Repair works of the station’s concrete vault and painting works at level -5.

PIRAEUS STATION 

The following works have been completed:

  • Waterproofing works underneath the foundation and at the perimeter walls
  • Concreting of platform and vertical parapet walls underneath the platforms.
  • Concreting of perimeter walls, inner parapet walls, intermediate slabs and columns

The following works are in progress:

  • Removal of struts and walers of the 1st row
  • Installation of formwork, reinforcement and concreting of the roof slab
  • Commencement of architectural finishes – construction of masonry walls and performance of plastering works

ROLOI SHAFT

The following works have been completed:

  • Construction of permanent lining (still pending is the termination at street level).

NATM ACCESS TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are put on hold:

  • Installation of doors at E/M level.

The following works are in progress:

  • Cleaning works
  • Cement mortar laying works at the ticketing level
  • Installation of floor granite slabs at the platform level
  • Installation of floor tiles in the personnel areas (ticketing level)
  • Preparatory works for painting at staircases 7 and 8
  • Conservation of the archaeological finds of the Project.

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, walls and platform slab.

The following works are in progress:

  • Cement mortar laying works at the platform level.

 STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Waterproofing of the permanent lining

The following works are put on hold:

  • Backfilling – compaction related works.

The following works are in progress:

  • Secondary concrete at the access gallery.

 DELIGIANNI SHAFT

 The following works have been completed:

  • Excavation and temporary retaining up to the final level
  • Waterproofing, construction of foundation slab and perimeter walls down to -3.0.

 PANEPISTIMIO SHAFT & VENTILATION TUNNEL

 The following works have been completed:

  • Excavation – temporary retaining
  • Concreting of the foundation of the shaft’s permanent lining
  • Concreting of the permanent lining of the connecting tunnel.