NEW RAILWAY Station: The works for the installation of E/M systems (fire extinguishing, water supply), as well as the construction of indoor partitions, are in progress.
DIMOKRATIAS Station (station and crossover): The works for the installation of doors at the station and well as painting works are in progress.
VENIZELOU Station: The works for burying antiquities within the main station box are in progress.
SINTRIVANI Station: The works for the construction of parapet walls in the surrounding area, at the north access, continue, while the works for the installation of E/M systems (water supply, sewage, fire fighting, fire detection, safety and intrusion detection system) are in progress.
PANEPISTIMIO Station: The E/M installation works (earthing, fire detection, telecommunications) are at an advanced stage, while painting works have commenced.
PAPAFI Station: The wall cladding works with granite slabs are at the completion stage, while the works related to the painting of the station and the shafts are at an advanced stage.
EFKLIDIS Station: Painting works at the platform level are in progress.
FLEMING Station: Plastering activities on masonry walls is in progress.
ANALIPSI Station & Crossover: Flooring works are at an advanced stage, while painting works of the roof and the walls of the Station’s platform level continue.
25 MARTIOU Station & Crossover: The construction of the staircase at the eastern emergency exit has been completed, while cladding works using granite slabs and works for the construction of industrial flooring continue.
VOULGARI Station: Works for the construction of balustrades at the emergency staircases are at an advanced stage.
NEA ELVETIA Station: Backfilling works, as well as cladding works with granite slabs are at an advanced stage.