ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. – ELLINIKO METRO S.A.

Kalamaria Project progress

August 2016

  • NOMARCHIA Station: The works for the construction of the foundation slab are in progress.
  • KALAMARIA Station: The works for the temporary retaining of the metal struts up to the 4th level are in progress.
  • ARETSOU Station: The installation of metal struts at the 2nd level has been completed. In progress are the excavation works up to the 3rd level.
  • The preparation and approval of designs are in progress.