- NOMARCHIA Station: Works for the phase A excavation, the construction of struts at level -1 and the perimeter piles cap beam are in progress;
 - NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam, as well as works for the diversion of PUO networks are in progress;
 - KALAMARIA Station: Works for the construction of perimeter piles at the eastern section of the station, as well as works for the diversion of PUO networks are in progress;
 - ARETSOU Station: The works for the construction of perimeter piles at a part of the station are in progress;
 - NEA KRINI Station: Works for the construction of a pumping station on the station raft, works for the construction of perimeter walls at level -3 and works for the removal of the 2nd row of struts, are in progress;
 - MIKRA Station: The boring of the 1st and 2nd NATM tunnel is completed;
 - MIKRA 2nd Crossover: Works for the construction of perimeter retaining piles and their cap beam are in progress;
 - MIKRA Forestation: Works for the diversion of PUO networks are in progress;
 - Terminal Shaft: The construction of perimeter piles is in progress;
 - Kritis shaft: The excavation of the 1st phase and the preparatory works for the installation of the 1st level metal struts is in progress;
 - Pontou shaft: The construction of perimeter piles and the configuration of the worksite area are in progress;
 - Preparation and approval of designs: in progress;
 - Areas expropriation at ARETSOU Station, MIKRA Station and MIKRA Forestation is still pending.
 
	