ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. – ELLINIKO METRO S.A.

Thessaloniki Base Project progress

March 2009

  • The assembly of the 2nd TBM was completed and its trial running commenced.
  • The construction of diaphragm walls was completed at SYNTRIVANI Station, while it is in progress at NEOS SIDIRODROMIKOS STATHMOS (completed at a percentage of 43%).
  • The worksite installation was completed at ANALIPSI Station and works related to PUO network diversions are in progress.