- The works for the construction of the floor slab at the forestation of the New Railway Station are in progress.
- The pile construction works at the north entrance of DIMOKRATIAS Station are in progress.
- The works for the construction of the floor slab at the 2 underground levels of FLEMING Station are in progress.
- The works for the construction of the temporary retaining piles have been completed.