- The works for the cleaning and maintenance of the cutter heads and the remaining facilities pertaining to the two Tunnel Boring Machines are at a completion stage.
- The works for the construction of EFKLIDIS Station shafts are in progress.
- Jet grouting works along ANALIPSI Station have been completed.