- The two Tunnel Boring Machines (TBMs) have currently bored a total of 10,200m of single track tunnel.
- The archaeological investigations have been completed at SYNTRIVANI Station and the works for the construction of the station’s northern access have commenced.
- The works for the repair of Kyrillos duct at the New Railway Station are in progress.
- Phase B of the archaeological excavations at AGHIA SOFIA Station has commenced.