- The construction of the roof slab at SINTRIVANI Station is in progress.
- The works for the construction of slab at level -2 at PANEPISTIMIO Station has commenced.
- The works for the installation of the escalator at the northern entrance of EFKLEIDIS Station are in progress.
- The archaeological excavation works in a section of EFKLEIDIS Station have been completed, while the works for the excavation of the entire station are about to commence.
- The works for relocating the PPC aerial networks into underground networks in the area of the Metro Depot.