Thessaloniki Base Project progress

April 2012

  • The completion percentage of the Civil Works for THESSALONIKI METRO Project reaches 42%, while the tunneling completion percentage is over 72%.
  • The architectural finishes works, as well as the works for the installation of the electromechanical equipment of the Project have recently commenced.
  • The archaeological excavations at four (4) locations of the Project (Dimokratias, Venizelou, Aghia Sofia and Depot) are in progress (progress rate: 70%).