- The construction of inner parapet walls at EFKLIDIS Station is in progress.
 - The excavation works at FLEMING Station are in progress.
 - The construction of diaphragm walls at ANALIPSI Station is in progress.
 - The ground slab at the 2nd basement of PANEPISTIMIO Station has been completed.
 - The construction of the roof slab at the intersection of DIMOKRATIAS Station has been completed.
 
	