- To date, the overall progress of the works in Thessaloniki Metro Project is 44.8%;
- Tunnel construction works have been completed by 73%;
- The archaeological excavation works have been completed by an overall percentage of 75%;
- Until the present day, the funds absorbed by the Thessaloniki Metro Project rise to the amount of 282.2 million EURO.