The entire Project: Activities took place concerning the following fields: smoke extraction (fan tests – performance measurements), platform screen doors (operational controls – tests), distribution surveillance systems (signals), surveillance systems of the remaining applications (signals – tests) and low voltage (commissioning of equipment).
Kritis Shaft: Works related to distribution (switchboards, connections), as well as works related to surveillance (signal tests) and low voltage (cabinets, connections) systems were executed.
NOMARHIA Station (Station & Crossover): In progress are works for the completion of architectural finishes as well as reinstatement works at street level.
In progress are electromechanical works related to infrastructure (trays), earthing (ducts), distribution (connections of equipment – switchboards), lighting (lighting fixtures), air conditioning (heating pump), lifts (construction of interior elevator), fire detection (switchboard), surveillance systems (connections, tests), low voltage (field equipment, connections) and fare related works (transport). In the Crossover area, works related to distribution (switchboard connections), ventilation (air ducts), surveillance systems (connections, tests) and low voltage (field equipment) have been executed.
KALAMARIA Station: In progress are works for the completion of reinstatement activities at street level. Moreover, under execution are electromechanical works related to infrastructure (trays), earthing (ducts), distribution (connections of equipment – switchboards), lighting (lighting fixtures), air conditioning (heating pump), lifts (construction of exterior lift), fire detection (switchboard, cables, layouts), surveillance systems (connections, tests) and low voltage (connections).
ARETSOU Station: In progress are electromechanical works related to infrastructure (grids), earthing (ducts), distribution (connections of equipment – switchboards), lighting (lighting fixtures), air conditioning (heat pump), lifts (construction of lift inside the station), fire detection (switchboard, cables, layout, tests), surveillance systems (connections, tests), low voltage (field equipment), as well as fare related works (transport, cables).
Pontou Shaft: The infrastructure works in this section and the lighting electromechanical works have been completed. The works for the connection of the supervision cabinets have also been completed.
NEA KRINI Station: In progress are electromechanical works related to earthing (ducts), distribution (connections of equipment – switchboards), lighting (lighting fixtures), air conditioning (unit), lifts (metal frames), surveillance systems (connections, tests), low voltage (field equipment).
MIKRA Station: In progress are electromechanical works related to earthing (ducts), distribution (connections of equipment – switchboards), lighting (lighting fixtures), air conditioning (network, heat pump), hydraulics (network), fire detection (network), lifts (metal frames), surveillance systems (cables, connections, tests) and low voltage (cables).
Tunnels: Completed are all infrastructure and trackwork related activities, as well as the majority of the electromechanical works. Moreover, electrical works (cables, switchboards, connections) and hydraulic works (firefighting network) have been executed at the connection of the Base Line with the extension to Kalamaria. Finally, in the section extending between Micra and Forestation, hydraulic works (pumping station) and works related to the surveillance systems (connections) have been executed.