Kalamaria Project progress

April 2025

MIKRA STATION: In progress are road surface reinstatement works in the station area (sidewalk and central traffic island finishes), as well as granite finishes works in all station levels.
NEA KRINI STATION: In progress are granite finishes works in all station levels. In progress are fibre optic cabling works at the Lighting and Auxiliary Substation (LAS 1SE4-1SE5) as well as medium voltage cabling works.
ARETSOU STATION: In progress are fibre optic cabling works in the Lighting and Auxiliary Substation (LAS 1SE4-1SE5) and medium voltage cabling works. Auxiliary circuits cabling works are also being executed in the Rectifier Substation. In progress are works for the installation of MV cables. Works for the installation of cables terminating at the lighting and auxiliary boxes (exit to tunnels) are being executed. In progress are works for the transportation of MV fields at the Lighting and Auxiliary Substation in ARETSOU Station.
TRACKWORK – TUNNELS: In progress are lighting and MV cabling works.