- NOMARCHIA Station (Station and Crossover): In progress are works for the implementation of the final traffic reinstatement (configuration of traffic islands and sidewalks) as well as painting works at street level.
- ARETSOU Station: Completed are works for the installation of glass panes, as well as the installation of doors at platform level, while in progress are slab paving works at street level.
- NEA KRINI Station: Completed are works for the installation of glass panes, as well as works for the installation of doors at the platform level.
- MIKRA Station (Station and Crossovers): In progress are road paving and slab paving works at street level, as well as works for the installation of glass panes at the concourse level.