ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. – ELLINIKO METRO S.A.

Piraeus Project progress

SEPTEMBER 2019

DOUBLE TRACK ΝΑΤΜ START TUNNEL

Works have been completed.

KOMNINOU SHAFT

The following works have been completed:

  • Masonry works, plastering works, door installation, industrial floor, painting works, installation of grids at street level, staircase balustrades, hatch
  • Reinstatement at street level

AGHIA VARVARA STATION

The following works are in progress:

  • Reinstatement at street level – Square level (granites, pathways, marble, fountain)
  • Installation of false ceilings at the platform and concourse levels
  • Cladding of walls and columns (steel, glass, etc.)

MEGALOU ALEXANDROU SHAFT

Works have been completed.

KORYDALLOS STATION

The following works are in progress:

  • Cladding of walls and columns
  • Installation of false ceiling
  • Installation of ventilation grids
  • Backfilling

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Final reinstatement at the station street level (– 0)
  • Installation of horizontal false ceiling panels at the concourse (– 2) and platform (– 3) levels of the Station
  • E/M works