Kalamaria Project progress

March 2024

  • KALAMARIA Station: In progress are works for the installation of glass panes at stainless steel rails, PSN tiles at the platform level and at level -2. Moreover, in progress are the works for the installation of cladding at the external escalators.
  • ARETSOU Station: In progress are the reinstatement works at street level, as well as works for the installation of granites at the platform level.
  • NEA KRINI Station: Completed are the works for the installation of handrails at the external escalators.
  • MICRA Station: In progress are the reinstatement works at street level, as well as works for the installation of manhole covers at the platform level. Moreover, in progress are works for the installation of trays and earthing of trays in the concourse area, as well as works for the installation of cladding at the external escalators.
  • TRACKWORK: In progress are works for the installation of the 3rd rail cable terminations. In addition, in progress are works for the completion of stray current earthing from the beginning of the Project up to NOMARCHIA Station, as well as works for the installation of lighting fixtures at “Nomarchia – Kalamaria” and “Kalamaria – Aretsou” sections.