TZAVELA SHAFT
The following woks have been completed:
- Permanent lining of the shaft’s bottom.
 - Permanent lining of the connecting tunnel.
 - Dismantling of the temporary steel arch for TBM tunnel support.
 - Permanent lining of the perimeter parapet wall of the
 - Permanent lining of the interior parapet wall and staircase.
 - Permanent lining of the slab at +8.57.
 
MANIATIKA STATION
CUT AND COVER SECTION OF THE STATION
The following woks have been completed:
- Waterproofing of the perimeter parapet walls.
 - Permanent lining of the foundation (level -4).
 - Permanent lining of the E/M slab (level -3).
 - Permanent lining of the ticketing area slab (level -2).
 - Permanent lining of staircase S
 - Permanent lining of the E/M slab (level -1).
 - Permanent lining of perimeter parapet walls and columns.
 - Permanent lining of the roof slab and staircase S3.
 - Construction of perimeter parapet walls of the station’s main entrance (street level) and of the inclined part of the main entrance (shed).
 
In progress are the following works:
- Waterproofing of the roof slab.
 - Construction of masonry walls and execution of plastering works at levels -4, -3, -1.
 
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel.
 - Permanent lining of the deepening area.
 - Permanent lining of the northern and southern headwall.
 - Construction of parapet walls and platform
 - Secondary grouting of the vault of the main tunnel of the station.
 - Filling of platform ducts with non-reinforced concrete.
 
PIRAEUS STATION
The following works have been completed:
- Waterproofing underneath the foundation.
 - Concreting of the foundation slab and placing of non-reinforced concrete over the foundation.
 
The following works are in progress:
- Installation of waterproofing at the station’s perimeter parapet walls and at the connecting area with the TBM tunnel.
 - Concreting of the station’s perimeter parapet walls and of the parapet walls underneath the platforms.
 - Concreting of platform slabs and of the E/M slab.
 - Removal of struts and sleepers of the 4th & 5th row and reinstallation of struts 5th row at a new location.
 - Concreting of interior walls and columns.
 
ROLOI SHAFT
The following works have been completed:
- Construction of foundation and permanent lining of perimeter parapet walls (still pending is the termination at street level).
 
NATM ACCESS TUNNEL
The following works have been completed:
- Concreting of the permanent lining.
 
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
 
The following works are put on hold:
- Installation of doors at the E/M floor.
 
In progress are the following works:
- Cleaning works.
 - Plastering works at the E/M floor and the concourse
 - Roof painting at platform
 - Placement of mortar at the pumping station walls.
 - Conservation of the archaeological finds of the Project.
 
UNDERGROUND SECTION OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.
 
The following works are in progress:
- Preparation works for painting the vault.
 
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.
 
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concreting and waterproofing.
 
The following works are in progress:
- Demolition of pile cap beam.
 
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level).
 - Secondary concrete at the staircases.
 
The following works are put on hold:
- Secondary concrete at the access gallery.
 
DELIGIANNI SHAFT
The following works have been completed:
- Excavation and temporary retaining up to the final level.
 - Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0.
 
PANEPISTIMIO SHAFT AND VENTILATION TUNNEL
The following works have been completed:
- Excavation – temporary retaining.
 - Concreting of the foundation of the shaft’s permanent lining.
 - Concreting of the permanent foundation of the connecting tunnel.
 