{"id":8168,"date":"2017-02-10T16:04:22","date_gmt":"2017-02-10T14:04:22","guid":{"rendered":"https:\/\/www.emetro.gr?p=8168"},"modified":"2024-06-25T13:21:57","modified_gmt":"2024-06-25T10:21:57","slug":"january-2017-4","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=8168&lang=en","title":{"rendered":"January 2017"},"content":{"rendered":"<p>\u2022 NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1.<\/p>\n<p>\u2022 NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level.<\/p>\n<p>\u2022 KALAMARIA Station: The construction of the pumping station walls and the waterproofing of the final level and the perimeter walls have been completed. In progress is the construction of the foundation slab.<\/p>\n<p>\u2022 ARETSOU Station: The construction of the pumping station walls has been completed, while in progress is the construction of the permanent lining from the invert slab to level -2.<\/p>\n<p>\u2022 NEA KRINI Station: In progress is the construction of the TBM trackbed.<\/p>\n<p>\u2022 MIKRA Station 1st Crossover: At the completion stage is the construction of perimeter walls up to level -1.<\/p>\n<p>\u2022 MIKRA Station: In progress is the construction of the invert slab and the TBM worksite installations.<\/p>\n<p>\u2022 MIKRA Forestation \u2013 Sections 4-5: The waterproofing of the final level is in progress.<\/p>\n<p>\u2022 Design preparation and approval in progress.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>\u2022 NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1. \u2022 NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level. \u2022 KALAMARIA Station: The construction of the pumping station walls and the waterproofing of the final level and the perimeter walls have been completed. In progress is the construction of the foundation slab. \u2022 ARETSOU Station: The construction of the pumping station walls has been completed, while in progress is the construction of the permanent lining from the invert slab to level -2. \u2022 NEA KRINI Station: In progress is the construction of the TBM trackbed. \u2022 MIKRA Station 1st Crossover: At the completion stage is the construction of perimeter walls up to level -1. \u2022 MIKRA Station: In progress is the construction of the invert slab and the TBM worksite installations. \u2022 MIKRA Forestation \u2013 Sections 4-5: The waterproofing of the final level is in progress. \u2022 Design preparation and approval in progress.<\/p>\n","protected":false},"author":4,"featured_media":8151,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[544],"tags":[],"class_list":["post-8168","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-kalamaria-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-scaled.jpg",2560,1397,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-scaled.jpg",2560,1397,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-scaled.jpg",2560,1397,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-300x164.jpg",300,164,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-1024x559.jpg",960,524,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-1536x838.jpg",1536,838,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-2048x1117.jpg",2048,1117,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-1140x622.jpg",1140,622,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2017\/02\/KALAMARIA-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"psymeonidou","author_link":"https:\/\/www.emetro.gr\/?author=4"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=544&#038;lang=en\" rel=\"category\">Kalamaria Project progress<\/a>","rttpg_excerpt":"\u2022 NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1. \u2022 NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level. \u2022 KALAMARIA Station: The construction of&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/8168","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=8168"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/8168\/revisions"}],"predecessor-version":[{"id":29024,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/8168\/revisions\/29024"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/8151"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=8168"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=8168"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=8168"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}