{"id":5779,"date":"2009-02-05T11:43:44","date_gmt":"2009-02-05T09:43:44","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=5779&#038;lang=en"},"modified":"2024-07-03T11:13:14","modified_gmt":"2024-07-03T08:13:14","slug":"january-2009","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=5779&lang=en","title":{"rendered":"January 2009"},"content":{"rendered":"<ul>\n<li style=\"text-align: justify;\">The running ot the first Tunnel Boring Machine commenced, while the assembly of the second TBM is in progress.<\/li>\n<li style=\"text-align: justify;\">The construction of diaphragm walls is at a completion stage:\n<ul>\n<li>DEMOKRATIAS Station:completed at a percentage of 99%<\/li>\n<li>SYNTRIVANI Station:completed at a percentage of 81%<\/li>\n<li>Forestation of NEOS SIDIRODROMIKOS STATHMOS:completed at a percentage of\u00a095%<\/li>\n<li>Branching towards Stavroupoli:completed at a percentage of 98%<\/li>\n<\/ul>\n<\/li>\n<li style=\"text-align: justify;\">The construction of diaphragm walls at AGHIA SOFIA Station is at an advanced stage (they are now completed at a percentage of 51%), while works related to the construction of retaining piles at PANEPISTIMIO Station were completed.<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>The running ot the first Tunnel Boring Machine commenced, while the assembly of the second TBM is in progress. The construction of diaphragm walls is at a completion stage: DEMOKRATIAS Station:completed at a percentage of 99% SYNTRIVANI Station:completed at a percentage of 81% Forestation of NEOS SIDIRODROMIKOS STATHMOS:completed at a percentage of\u00a095% Branching towards Stavroupoli:completed at a percentage of 98% The construction of diaphragm walls at AGHIA SOFIA Station is at an advanced stage (they are now completed at a percentage of 51%), while works related to the construction of retaining piles at PANEPISTIMIO Station were completed.<\/p>\n","protected":false},"author":9,"featured_media":3570,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[79],"tags":[],"class_list":["post-5779","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-thessaloniki-base-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG-200x300.jpg",200,300,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG-533x540.jpg",533,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG.jpg",533,800,false],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_thess_progress_jan09_LG-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"elinaki","author_link":"https:\/\/www.emetro.gr\/?author=9"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=79&#038;lang=en\" rel=\"category\">Thessaloniki Base Project progress<\/a>","rttpg_excerpt":"The running ot the first Tunnel Boring Machine commenced, while the assembly of the second TBM is in progress. The construction of diaphragm walls is at a completion stage: DEMOKRATIAS Station:completed at a percentage of 99% SYNTRIVANI Station:completed at a percentage of 81% Forestation of NEOS SIDIRODROMIKOS STATHMOS:completed at a percentage of\u00a095% Branching towards Stavroupoli:completed&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/5779","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/9"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=5779"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/5779\/revisions"}],"predecessor-version":[{"id":31337,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/5779\/revisions\/31337"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/3570"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=5779"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=5779"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=5779"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}