{"id":5637,"date":"2014-08-22T07:56:42","date_gmt":"2014-08-22T04:56:42","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=5637&#038;lang=en"},"modified":"2024-05-28T13:35:32","modified_gmt":"2024-05-28T10:35:32","slug":"july-2014-2","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=5637&lang=en","title":{"rendered":"July 2014"},"content":{"rendered":"<ul>\n<li style=\"text-align: justify;\">NEW RAILWAY Station: The construction of the NW &amp; NE shaft, as well as the restoration of openings (level 1) at the crossover, are in progress;<\/li>\n<li style=\"text-align: justify;\">DIMOKRATIAS Station: The construction of the southern part of the roof slab was completed;<\/li>\n<li style=\"text-align: justify;\">PANEPISTIMIO Station: The excavation of level 4 has commenced;<\/li>\n<li style=\"text-align: justify;\">PAPAFI Station: The works for the installation of the 4th level of struts have commenced;<\/li>\n<li style=\"text-align: justify;\">EFKLIDIS Station: The demolition of the TBM false tunnel at level 4 was completed;<\/li>\n<li style=\"text-align: justify;\">FLEMING Station: The excavation at the last level (level -3) was completed;<\/li>\n<li style=\"text-align: justify;\">ANALIPSI Station &amp; Crossover: The excavation and construction of the slab at level 3, construction works at ventilation shafts 1, 2 &amp; 3, as well as the retaining &amp; excavation works at the eastern access are in progress;<\/li>\n<li style=\"text-align: justify;\">VOULGARI Station: PUO network diversions have commenced;<\/li>\n<li style=\"text-align: justify;\">NEA ELVETIA Station &amp; Crossover: The works for the construction of the foundation slab at the crossover have commenced;<\/li>\n<li style=\"text-align: justify;\">DEPOT: The works for the construction of the 1st basement of building I were completed. The following works are in progress: excavation and retaining of building II-OCC, construction of the ground floor slab at the train passing through area, construction of parapet walls and columns of building I and the archaeological excavation at a part of building II.<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>NEW RAILWAY Station: The construction of the NW &amp; NE shaft, as well as the restoration of openings (level 1) at the crossover, are in progress; DIMOKRATIAS Station: The construction of the southern part of the roof slab was completed; PANEPISTIMIO Station: The excavation of level 4 has commenced; PAPAFI Station: The works for the installation of the 4th level of struts have commenced; EFKLIDIS Station: The demolition of the TBM false tunnel at level 4 was completed; FLEMING Station: The excavation at the last level (level -3) was completed; ANALIPSI Station &amp; Crossover: The excavation and construction of the slab at level 3, construction works at ventilation shafts 1, 2 &amp; 3, as well as the retaining &amp; excavation works at the eastern access are in progress; VOULGARI Station: PUO network diversions have commenced; NEA ELVETIA Station &amp; Crossover: The works for the construction of the foundation slab at the crossover have commenced; DEPOT: The works for the construction of the 1st basement of building I were completed. The following works are in progress: excavation and retaining of building II-OCC, construction of the ground floor slab at the train passing through area, construction of parapet walls and columns of building I and the archaeological excavation at a part of building II.<\/p>\n","protected":false},"author":9,"featured_media":3375,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[79],"tags":[],"class_list":["post-5637","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-thessaloniki-base-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",1024,682,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",1024,682,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",1024,682,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG-300x200.jpg",300,200,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",960,639,false],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",1024,682,false],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",1024,682,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG-1024x540.jpg",1024,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG.jpg",1024,682,false],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2016\/07\/AM_Thess_progress_July14_LG-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"elinaki","author_link":"https:\/\/www.emetro.gr\/?author=9"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=79&#038;lang=en\" rel=\"category\">Thessaloniki Base Project progress<\/a>","rttpg_excerpt":"NEW RAILWAY Station: The construction of the NW &amp; NE shaft, as well as the restoration of openings (level 1) at the crossover, are in progress; DIMOKRATIAS Station: The construction of the southern part of the roof slab was completed; PANEPISTIMIO Station: The excavation of level 4 has commenced; PAPAFI Station: The works for the&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/5637","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/9"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=5637"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/5637\/revisions"}],"predecessor-version":[{"id":28208,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/5637\/revisions\/28208"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/3375"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=5637"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=5637"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=5637"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}