{"id":34880,"date":"2025-12-09T11:13:45","date_gmt":"2025-12-09T09:13:45","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=34880"},"modified":"2025-12-09T11:13:46","modified_gmt":"2025-12-09T09:13:46","slug":"october-2025","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=34880&lang=en","title":{"rendered":"October 2025"},"content":{"rendered":"\n<p><strong>Kritis Shaft:<\/strong> All infrastructure related activities of this section, as well as the electromechanical works pertaining to lighting, hydraulics, ventilation and low voltage distribution have been completed. The execution of activities regarding the interconnection at signals level and the power supply in the ventilation facility (transformers) is anticipated.<\/p>\n\n\n\n<p><strong>NOMARHIA Station:<\/strong> All infrastructure related activities of this Station, as well as the medium voltage electrotechnical works, fire extinguishing, hydraulics and Platform Screen Doors (PSDs) have been completed. In progress are the works for the completion of the architectural finishes and reinstatement at street level.&nbsp;<\/p>\n\n\n\n<p>In addition, in progress are the electromechanical works for distribution (installation \u2013 connection of switchboard supply cables and devices supply cables), for integration of electrical features, ventilation (air-ducts\u2019 networks), air-conditioning (piping) and low voltage (installation of signal cables).<\/p>\n\n\n\n<p>Anticipated is the execution of activities regarding the activation (energization) of the LAS Substation, the connection of cables, certain switchboards, lighting in the concourse areas, lifts (outdoor \u2013 indoor), the completion of fire detection, as well as the control subsystems (field equipment, interface with center platforms).<\/p>\n\n\n\n<p><strong>KALAMARIA Station: <\/strong>All infrastructure, architectural finishes and hydraulics related activities of this Station have been completed. In progress are the works pertaining to the completion of reinstatement at street level.<\/p>\n\n\n\n<p>The electromechanical works pertaining to medium and low voltage, ventilation systems, firefighting, automatic fire extinguishing and PSD systems have been completed.<\/p>\n\n\n\n<p>In progress are the electromechanical works for distribution (installation \u2013 connection of switchboard supply cables and devices supply cables), for integration of electrical features, hydraulics (pumps), radio communication and low voltage (installation of signal cables and surveillance \u2013 supervision applications).<\/p>\n\n\n\n<p>Anticipated is the execution of activities regarding the activation (energization) of the LAS Substation, the connection of cables, certain switchboards, lighting in the concourse areas, lifts (outdoor \u2013 indoor), the completion of fire detection, as well as the control subsystems (cables, field equipment, interface with center platforms).<\/p>\n\n\n\n<p><strong>ARETSOU Station: <\/strong>All infrastructure related activities of this Station, as well as the electromechanical works pertaining to medium and low voltage, ventilation systems, firefighting, automatic fire extinguishing and PSD systems have been completed.<\/p>\n\n\n\n<p>In progress are the works pertaining to the completion of architectural finishes and reinstatement at street level, as well as the electromechanical works for distribution (connection of devices supply cables), lighting (fixing of lighting fixtures), ventilation \u2013 air conditioning (construction of networks), lifts (full construction), fire detection (connections) and low voltage (installation of surveillance \u2013 supervision applications\u2019 cables).<\/p>\n\n\n\n<p><strong>NEA KRINI Station: <\/strong>The electromechanical works pertaining to themediumand low voltage, ventilation systems, firefighting, automatic fire extinguishing and PSD systems have been completed.<\/p>\n\n\n\n<p>In progress are the works pertaining to the electromechanical works for distribution (connection of devices supply cables), lighting (fixing of lighting fixtures), ventilation \u2013 air conditioning (construction of networks), radio communication and low voltage (installation of signals\u2019 and surveillance \u2013 supervision applications\u2019 cables).<\/p>\n\n\n\n<p><strong>MIKRA Station: <\/strong>In progress are the works pertaining to the electromechanical works for distribution (installation &#8211; connection of switchboard supply cables and devices supply cables), lighting (indoor lighting fixtures), integration of electrical features, ventilation \u2013 air conditioning (construction of networks), hydraulics (pumps), radio communication and low voltage (installation of signals\u2019 and surveillance \u2013 supervision applications\u2019 cables).<\/p>\n\n\n\n<p><strong>Tunnels: <\/strong>All infrastructure and trackwork related activities have been completed. At their completion stage are the electromechanical works pertaining to low voltage distribution, earthing, tunnel traction and firefighting systems.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Kritis Shaft: All infrastructure related activities of this section, as well as the electromechanical works pertaining to lighting, hydraulics, ventilation and low voltage distribution have been completed. The execution of activities regarding the interconnection at signals level and the power supply in the ventilation facility (transformers) is anticipated. NOMARHIA Station: All infrastructure related activities of this Station, as well as the medium voltage electrotechnical works, fire extinguishing, hydraulics and Platform Screen Doors (PSDs) have been completed. In progress are the works for the completion of the architectural finishes and reinstatement at street level.&nbsp; In addition, in progress are the electromechanical works for distribution (installation \u2013 connection of switchboard supply cables and devices supply cables), for integration of electrical features, ventilation (air-ducts\u2019 networks), air-conditioning (piping) and low voltage (installation of signal cables). Anticipated is the execution of activities regarding the activation (energization) of the LAS Substation, the connection of cables, certain switchboards, lighting in the concourse areas, lifts (outdoor \u2013 indoor), the completion of fire detection, as well as the control subsystems (field equipment, interface with center platforms). KALAMARIA Station: All infrastructure, architectural finishes and hydraulics related activities of this Station have been completed. In progress are the works pertaining to the completion of reinstatement at street level. The electromechanical works pertaining to medium and low voltage, ventilation systems, firefighting, automatic fire extinguishing and PSD systems have been completed. In progress are the electromechanical works for distribution (installation \u2013 connection of switchboard supply cables and devices supply cables), for integration of electrical features, hydraulics (pumps), radio communication and low voltage (installation of signal cables and surveillance \u2013 supervision applications). Anticipated is the execution of activities regarding the activation (energization) of the LAS Substation, the connection of cables, certain switchboards, lighting in the concourse areas, lifts (outdoor \u2013 indoor), the completion of fire detection, as well as the control subsystems (cables, field equipment, interface with center platforms). ARETSOU Station: All infrastructure related activities of this Station, as well as the electromechanical works pertaining to medium and low voltage, ventilation systems, firefighting, automatic fire extinguishing and PSD systems have been completed. In progress are the works pertaining to the completion of architectural finishes and reinstatement at street level, as well as the electromechanical works for distribution (connection of devices supply cables), lighting (fixing of lighting fixtures), ventilation \u2013 air conditioning (construction of networks), lifts (full construction), fire detection (connections) and low voltage (installation of surveillance \u2013 supervision applications\u2019 cables). NEA KRINI Station: The electromechanical works pertaining to themediumand low voltage, ventilation systems, firefighting, automatic fire extinguishing and PSD systems have been completed. In progress are the works pertaining to the electromechanical works for distribution (connection of devices supply cables), lighting (fixing of lighting fixtures), ventilation \u2013 air conditioning (construction of networks), radio communication and low voltage (installation of signals\u2019 and surveillance \u2013 supervision applications\u2019 cables). MIKRA Station: In progress are the works pertaining to the electromechanical works for distribution (installation &#8211; connection of switchboard supply cables and devices supply cables), lighting (indoor lighting fixtures), integration of electrical features, ventilation \u2013 air conditioning (construction of networks), hydraulics (pumps), radio communication and low voltage (installation of signals\u2019 and surveillance \u2013 supervision applications\u2019 cables). Tunnels: All infrastructure and trackwork related activities have been completed. At their completion stage are the electromechanical works pertaining to low voltage distribution, earthing, tunnel traction and firefighting systems.<\/p>\n","protected":false},"author":4,"featured_media":34866,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[544],"tags":[],"class_list":["post-34880","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-kalamaria-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-scaled.jpg",2560,1210,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-scaled.jpg",2560,1210,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-scaled.jpg",2560,1210,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-300x142.jpg",300,142,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-1024x484.jpg",960,454,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-1536x726.jpg",1536,726,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-2048x968.jpg",2048,968,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-1140x539.jpg",1140,539,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2025\/12\/KALAMARIA_10_2025-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"psymeonidou","author_link":"https:\/\/www.emetro.gr\/?author=4"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=544&#038;lang=en\" rel=\"category\">Kalamaria Project progress<\/a>","rttpg_excerpt":"Kritis Shaft: All infrastructure related activities of this section, as well as the electromechanical works pertaining to lighting, hydraulics, ventilation and low voltage distribution have been completed. The execution of activities regarding the interconnection at signals level and the power supply in the ventilation facility (transformers) is anticipated. NOMARHIA Station: All infrastructure related activities of&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/34880","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=34880"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/34880\/revisions"}],"predecessor-version":[{"id":34881,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/34880\/revisions\/34881"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/34866"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=34880"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=34880"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=34880"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}