{"id":31917,"date":"2024-09-03T13:03:08","date_gmt":"2024-09-03T10:03:08","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=31917"},"modified":"2024-09-27T13:03:37","modified_gmt":"2024-09-27T10:03:37","slug":"july-2024-2","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=31917&lang=en","title":{"rendered":"July 2024"},"content":{"rendered":"\n<p>\u2022 <strong>NOMARCHIA Station (Station &amp; Crossover):<\/strong> In the Crossover area, in progress are works for the installation of tiles, as well as works for the waterproofing of the water tank.<\/p>\n\n\n\n<p>\u2022<strong> ARETSOU Station:<\/strong> In progress are works for the installation of floor granites at the platform level.<\/p>\n\n\n\n<p>\u2022<strong> MICRA Station:<\/strong> In progress are works for the installation of cabling of the fire detection system.<\/p>\n\n\n\n<p><strong>TRACKWORK:<\/strong> In progress are measurements of the safety related dimensions of turnouts and crossovers, as well as gauge controls and guard rail controls.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>\u2022 NOMARCHIA Station (Station &amp; Crossover): In the Crossover area, in progress are works for the installation of tiles, as well as works for the waterproofing of the water tank. \u2022 ARETSOU Station: In progress are works for the installation of floor granites at the platform level. \u2022 MICRA Station: In progress are works for the installation of cabling of the fire detection system. TRACKWORK: In progress are measurements of the safety related dimensions of turnouts and crossovers, as well as gauge controls and guard rail controls.<\/p>\n","protected":false},"author":4,"featured_media":31915,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[544],"tags":[],"class_list":["post-31917","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-kalamaria-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024-284x300.jpg",284,300,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024-673x540.jpg",673,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024.jpg",673,711,false],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2024\/09\/KALAMARIA_07_2024-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"psymeonidou","author_link":"https:\/\/www.emetro.gr\/?author=4"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=544&#038;lang=en\" rel=\"category\">Kalamaria Project progress<\/a>","rttpg_excerpt":"\u2022 NOMARCHIA Station (Station &amp; Crossover): In the Crossover area, in progress are works for the installation of tiles, as well as works for the waterproofing of the water tank. \u2022 ARETSOU Station: In progress are works for the installation of floor granites at the platform level. \u2022 MICRA Station: In progress are works for&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/31917","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=31917"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/31917\/revisions"}],"predecessor-version":[{"id":31918,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/31917\/revisions\/31918"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/31915"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=31917"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=31917"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=31917"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}